JHC_ Tesco Road Surface Upgrade Genco_Hove_17.03.25_ RAMs_R1

access equipment will be checked/ inspected before use for any obvious defects Access and egress routes to be kept clear at all times. All debris will be cleared as soon as reasonably practicable as works proceed

During our activities appropriate signage displayed. Physical barriers to be erected to prevent access.

Hard hat, safety boots, high visibility vests and suitable gloves to be worn at all times

Manual Handling

3 3 9

JHC will avoid/ eliminate the need to manual handle where possible.

1

3

3

Operatives

Musculoskeletal injuries. Falling/ tripping

Mechanical equipment to be used where possible to eliminate manual handling.

Hiab’s / mechanical aids to be used for unloading and loading materials from the delivery trucks where possible.

Where mechanical equipment is not possible loads will be divided and reduced. The loads will be split into smaller, more manageable sizes for transportation.

All operatives to be trained in the correct techniques of manual handling.

Access and egress routes to be kept clear of obstructions at all times.

Hard hat, safety boots, high visibility vests and sufficient gloves to be worn at all times.

JHC_Tesco Hove Ground Works Upgrade R1