Section 2 – Scope of Works & Introduction
Introduction
This is a statement has been developed to provide a safe system of work for the persons undertaking the works, and anyone who may be affected by our working activities. This methodology must be adhered to at all times, any significant deviation from this safe system of works, must first be authorised by your supervisor. JHC has been appointment by Genco Construction to undertake the working activities within Tesco public thoroughfare. All main works will be undertaken during normal working hours timeframe, which will be agreed by the Genco Construction project teams prior to commencing.
Site Set Up – Heras Segregation Within Car Park –
The JHC will ensure a full exclusion zone and safety signage will be set up/ displayed prior to these works commencing. JHC operatives will comply with the HSG151 & SG 34 Protection of the public guidance’s at all times .
Only trained/ competent scaffolding personnel will be undertaking the erection, dismantle, adaptation and installation of the Heras structure.
All components will be inspected for obvious defects prior to installation and adaptation by the operators. This quality check is also undertaken within the yard.
JHC will continue to monitor the weather conditions during these working operations and the supervisor will cease works if he/ she deems it necessary.
Operatives will position foot blocks to designated areas at approximately 3 m or length of panels, then place the fence frames into foot block holes, after this process has been repeated, fix link brackets to fence uprights tying together fence frames. 2 link brackets per fence panel as per the manufacture’s guidance.
Depending on the wind loads and position if the Heras fence panels, additional restrains may be applied. This will be discussed with the client team prior and align with the manufacturer’s guidance.
No part of the Heras will be left in an unsafe or unstable condition and shall be secured at all times during the erection and dismantling process. All loose materials shall be stored and contained within secured areas or removed from site. Regular Inspections shall be undertaken.