Hiranandani Fortune City, Panvel - Newsletter - October 2020

Project: Artemis

Project: Zeus

Construction Updates

All slab works completed Lift machine room completed. Above terrace works such as terrace waterproofing work in progress Lift installation completed, presently undergoing testing Plumbing works, fire fighting equipment installation, internal and lobby finishing works ongoing

Click on video thumbnail for 3-BHK finished apartment

Actual image

Actual image

External facade (above) and above terrace works in progress (bottom left) - Project Zeus

Construction Updates

All slab works completed Above terrace and lift machine room work in progress Plumbing works, fire fighting equipment installation, internal and lobby finishing works ongoing

Click on video thumbnail for 2-BHK finished apartment

Actual image

External facade (above) and above terrace works in progress (above right) - Project Artemis

Actual image