Project: Hera
Project: Vesta
Construction Updates
All slab works completed Above terrace and lift machine room work in progress Plumbing works, fire fighting equipment installation, internal and lobby finishing works ongoing
Click on video thumbnail for 1-BHK finished apartment
Actual image
Actual image
External facade (above) - Project Hera
Construction Updates
All slab works completed Above terrace and lift machine room work in progress Plumbing works, fire fighting equipment installation, internal and lobby finishing works ongoing
Click on video thumbnail for 1-BHK finished apartment
Actual image
External facade (above) and above terrace works in progress (above left) - Project Vesta
Click on video thumbnail for Studio finished apartment
Made with FlippingBook flipbook maker