• The proposed mitigation actions are specific and actionable. • It is evident that actions, including those carried over from the previous plan, were evaluated and re- prioritized. • Stakeholder and public input are evident in the list of mitigation actions. Connecting the planning process to the mitigation strategies.
Element D: Plan Update, Evaluation, and Implementation ( Plan Updates Only ) Plan Strengths • Table 2.9 provides a status for completed and deleted actions from the 2015 Wake County HMP, which includes status comments and/or explanations, as information is available. • The update, evaluation, and implementation process are documented.