Technical training
Blade Repair Standard / V5 23022026
Electrical insulating protective gloves required
Chemical protective gloves required
Additional information
This Service Work Instruction contains global documentation only.
All measurements are given in SI units (metric system).
All Joint ID definitions can be found in the related platform Maintenance Manual.
Lockout tagout (LOTO) equipment may vary due to local requirements. Apply DO-NOT-OPERATE signs correctly when used.
Ensure a safe work environment. Consider all risks when working.
Recoating Time
Actual recoating times can be shorter or longer depending on film thickness, ventilation, moisture, or other local conditions.
Surface Temperature & 50 % RH
Minimum Drying Time
Maximum Drying Time
5 °C
10 h
5 days 4 days 3 days 2 days
10 °C 20 °C 30 °C 40 °C
5 h 3 h
1.5 h 0.5 h
1 day
Table 2: Recoating Time
Curing Schedule Surface Temperature & 50 % RH
Curing Time
5 °C
20 h
Global Wind Organisation / www.globalwindsafety.org
170 / 187