COMPLETED TO DATE
site preparation & demolition cistern poured and backfilled under-slab plumbing wood framing & building envelope drywall ICF walls and cement floor for new section covered-entrance stair tower
2-level catwalk HVAC system sprinkler system electrical and mechanical systems exterior siding triple-glazed windows solar photovoltaic system security system sprung floor system retractable seating system
Installing Art Gallery lights
IN PROCESS
architectural woodwork cabinetry doors, finishes & hardware
UPCOMING
landscaping asphalt, curb & sidewalk signage & donor wall theatre equipment installation
Artistic Director Emmy Alcorn tracking the progress Photo: Hilary Hendsbee