Technical training
Basic Technical Training Standard / V11 10032026
The aim of this lesson is to give the participants an overview of the installation activities of a wind farm and enable the participants to handle installation hazards in an installation environment.
ELEMENT 2.1 - INSTALLATION OVERVIEW
Learning objective:
24) The participants can describe the main installation activities during wind turbine installation (Knowledge, basic level)
The instructor shall:
Present the main activities required for the installation of turbines. This will include:
a.
incoming inspection of components
b.
unloading
c.
storage and preservation
d.
repair
e.
preparation
f.
pre-assembly
g.
lifting / assembly
h.
tightening
i.
cable work
j.
finishing (Mechanical, Hydraulic and Electrical)
Ask the participants relevant questions about the main activities required for the installation of turbines
The participants shall:
Describe in their own words the main activities required for the installation of turbines