CC Case Study_Mine Ditch Lining - Myra Falls - Titan

®

Myra Falls CC Channel Lining

Aerial footage showing completed CC lined channel in relation to the mine

Summary The installation took 6 weeks to complete with an average crew size of 6 men and daily temperatures up to 34°C. The client was satisfied with the product and the minimal amount of specialist training or equipment required. In addition to this, the speed of installation meant the project was completed before the heavier precipitation arrived at the mine in early October which may have caused significant project delays.