Skip the Cleanroom Queue: Rapid Operational Readiness

It is clear the capabilities that modular brings to the construction process, allowing a cleanroom facility which looks like more than just a temporary building, adding value to the organisation on a whole other level.

Ardmac were commissioned to build a two- storey cleanroom with a production space of 87m2 on each floor. The ground floor was to be used for production and the first floor was a plant area. The challenge was delivering the Class 7 & 8 (BSL2) cleanroom building just 5 months with 95% completed and tested. Key deliverables were for it to have a flexible HVAC system, be scalable to grow, suitable for construction inside a building or externally to the building and a replicable design which enabled future growth.