AUTHORITY PROJECT SUMMARY HT-3019-0000 BHT Maintenance/Auto Building HVAC and Roof Replacement

PIN NUMBER CONTRACT NUMBER CONTRACT TITLE

2560 HT-3019-0000 BHT Maintenance/Auto Building HVAC and Roof Replacement

PROJECT SUMMARY

This project includes the replacement of the HVAC system and Roof at the Maintenance/Auto Building at Baltimore Harbor Tunnel Facility. Project work includes, but is not limited to: 1. Replacement of the HVAC system. 2. Upgrades of roofing systems: the existing membrane roof will be removed and replaced, and the existing metal roof will be repaired and refinished. 3. Upgrades of interior ceiling, lighting, fire alarm system, and other building elements that are impacted by the HVAC equipment replacement.

SCHEDULE

BID RESULTS

BID AMOUNT ($) % VARIANCE TO EE

ADVERTISEMENT DATE

11/19/2024

Fresh Air Concepts, LLC.

$5,330,000.00 $7,326,000.00 $8,933,000.00 $8,937,000.00

-14% 18% 43% 43%

ANTICIPATED NOTICE TO PROCEED DATE

Aug-25

Detwiler Roofing

DURATION (CALENDER DAYS)

730

W.M. Schlosser Co., Inc. Nichols Contracting, Inc.

ENGINEER'S ESTIMATE (EE)

$6,230,700.00

ADVERTISED

PROPOSED GOAL (%)

NO ☒

BID PROTEST

YES

MBE PARTICIPATION

GOAL (%)

OVERALL MBE

24.00%

24.00% 13.00%

FUNDING SOURCE

100.00% TOLL REVENUE

AFRICAN AMERICAN ASIAN AMERICAN HISPANIC AMERICAN

8.00% 0.00% 0.00%

0.00% 0.00%

WOMEN

11.00%

11.00%

VSBE

1.00%

1.00%