SYCAMORE PARK STUDENT ACCOMMODATION, QUEEN’S UNIVERSITY BELFAST

KILLOWEN CONTRACTS EXCELS IN A TIME-CRITICAL PROJECT, REVITALISING STUDENT ACCOMMODATION FOR QUEEN’S UNIVERSITY BELFAST… KILLOWEN CONTRACTS DELIVERS QUEEN’S UNIVERSITY STUDENT LIVING UPGRADE

W hen Queen’s University Belfast needed a fast-track refit project at its Sycamore Park Student Accommodation, it appointed long-term construction partner, Killowen Contracts Ltd, to deliver the large-scale, time-critical programme. In total, the Newry-based firm revamped 19 kitchens, equipping them with modern appliances and refurbished 198 ensuites. The £1.20 million project was completed within a strict 12-week programme. The construction itself was relatively straightforward, with the main challenge lying in managing the programme’s tight timeframe and volume of work.

“We needed to complete the work during the summer recess to ensure everything was ready for the students’ return in September 2023,” explained Andrew Knapton, Director for Killowen Contracts. “We decided to get a head start on the project by beginning our assessments before the students vacated the buildings. This allowed us to understand the scope of work required and create fabrication drawings. By doing so, we had new kitchen installations underway by the second week of the programme. “Our approach involved engaging our trusted supply chain early on. We also collaborated directly with Queen’s

University, leveraging our strong working relationship with them. This early engagement enabled us to conduct on- site assessments, take measurements, draft drawings and secure approvals before commencing work. With preparations in full swing, we initiated production even before arriving on-site, allowing us to start the fit-out process promptly.” Electrical works included replacement of light fittings and appliances and installation of new sockets and TVs. The mechanical aspect involved the installation of new Integrated Panel Systems (IPS) shower units.

“The £1.20 million project was completed within a strict 12-week programme.”