Master Transportation Plan Medium-Term Modeling Analysis
Table A- 1: Medium-Term Analysis List of Projects
No.
Facility / Project Name WJ Boaz Rd.(west half) (2022)
From
Description
Coded (Y/N)
To
1
Boat Club Rd.
Elkins School Rd.
Design and construction of 1.03 miles of a 4- lane divided thoroughfare with curb and gutter, drainage, streetlights, and shared paths Reconstruct existing 2-lane undivided to 4- lane divided roadway Design and ROW of 0.7 miles of a 4-lane divided roadway with curb and gutter, drainage, streetlights, and shared paths Construct a new 4- lane divided roadway with grade- separation at RR and Bus 287. Connect to Old Decautur and Bus 287. Reconstruct two (2) lane undivided to four (4)-lane divided roadway. Reconstruct two (2) lane undivided to four (4)-lane divided roadway.
Y
2
Meacham Blvd Phase II (West) (2022) E. Bailey Boswell Rd (2022)
I-35W
Blue Mound Road
Y
3
Horseman Dr
Blue Mound Rd/FM 156
Y
Scenario 1
4
Heritage Trace Parkway I (2022)
@BUS 287 (Saginaw Blvd)/Old Decatur
Wagley Robertson Rd
Y
5
Bonds Ranch Road
FM 1220
N. Saginaw Blvd
Y
6
Bonds Ranch Road
East of BNSF/UP RR
Wagley Robertson Rd
Y