Heritage Trace Parkway Wagley Robertson Road to Copper Meadow Drive
ENVIRONMENTAL CONSIDERATIONS » Floodplain and Wetland Considerations: Portions of the project area fall within FEMA- designated Zone A and Zone AE floodplains, which will influence the drainage design. A wetland delineation is recommended to determine if Previous oil and gas wells near the project area. A Phase I Environmental Site Assessment (ESA) is recommended. PROJECT COMPLEXITY The top challenges include railroad coordination, complex bridge design, floodplain impacts, potential wetlands, and utility relocation. jurisdictional wetlands exists. » Environmental Due Diligence:
PROSPECTIVE PARTNERS City of Fort Worth (2026 & 2030 Bonds)
U.S. Department of Transportation
High
PROJECT TIMELINE 2026 2027 2028 2029 2030 2031 2032
Design (30%-100%)
NEPA
Construction - East Segment
Construction - West Segment (beyond 2032)
ROW
Advertise/City Council Selection
Utility
Project Timeline is subject to change
www.movingamillion.org
Made with FlippingBook - professional solution for displaying marketing and sales documents online