AMP 2019-2029

Electricity Asset Management Plan 2019-2029

269

Vector Limited://

Forecast Capacity (Schedule 12b)

Vector Electricity

Company Name

1 April 2019 – 31 March 2029

AMP Planning Period

SCHEDULE 12b: REPORT ON FORECAST CAPACITY

This schedule requires a breakdown of currentand forecastcapacity and utilisation for each zonesubstation and currentdistribution transformer capacity.Thedata provided should beconsistentwith the information provided in theAMP. Information provided in this tableshould relate to theoperation of thenetwork in its normal steady stateconfiguration.

sch ref

12b(i): System Growth - Zone Substations

7

Utilisation of Installed Firm Capacity %

Utilisation of Installed Firm Capacity +5yrs %

Installed Firm Capacity +5 years (MVA)

Installed Firm Capacity Constraint +5 years (cause)

Installed Firm Capacity (MVA)

Security of Supply Classification (type)

8

Current Peak Load (MVA)

Transfer Capacity (MVA)

Existing Zone Substations

Explanation

Atkinson Road Auckland Airport

Meets Vector security criteria Meets customers security criteria

9

21 19 28 27 14 13 24 11 18 23 17 22 22 11 26 17 16 11 16 9 3 16 13 40 26 10 15 18 16 20 17 14 9 9 21

21 N-1 25 N-1

21 10 26 21 15 13 24 12 18 23 10 15 15 11 25 17 9 3 34 13 28 15 10 15 18 16 20 17 11 9 7 10 16 17

99% 75%

24 25 24 24 24 14 24 18 18 24 22 24 24

85% No constraintwithin +5 years

10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 31 32 33 34 35 36 37 38 39 40 41 42 43 30

112% Other

Avondale

Meets Vector security criteria when combined with 11kVbackup Meets Vector security criteria when combined with 11kVbackup

24 N-1 switched 24 N-1 switched

118% 112%

122% No constraintwithin +5 years 113% No constraintwithin +5 years No constraintwithin +5 years 56% No constraintwithin +5 years 94% No constraintwithin +5 years 97% No constraintwithin +5 years 84% No constraintwithin +5 years 99% No constraintwithin +5 years 96% No constraintwithin +5 years 77% No constraintwithin +5 years 93% No constraintwithin +5 years 93% No constraintwithin +5 years No constraintwithin +5 years 91% No constraintwithin +5 years 123% No constraintwithin +5 years 102% No constraintwithin +5 years 83% No constraintwithin +5 years 78% No constraintwithin +5 years No constraintwithin +5 years 67% No constraintwithin +5 years No constraintwithin +5 years 90% No constraintwithin +5 years No constraintwithin +5 years 124% No constraintwithin +5 years No constraintwithin +5 years 85% No constraintwithin +5 years 121% No constraintwithin +5 years 61% No constraintwithin +5 years 66% No constraintwithin +5 years 89% No constraintwithin +5 years 79% No constraintwithin +5 years 51% No constraintwithin +5 years 115% No constraintwithin +5 years

Bairds

Balmain Balmoral Belmont Birkdale Brickworks Browns Bay Bush Road Carbine Chevalier Clendon Clevedon Coatesville

Meets Vector security criteria Meets Vector security criteria Meets Vector security criteria Meets Vector security criteria

- N

-

-

24 N-1 14 N-1

56% 96%

24 N-1 switched - N-1 switched 10 N-1 switched

101%

Constraint relieved by the installation of thesecond transformer

-

Constraint relieved by transformer capacity upgrade

184%

Meets Vector security criteria when combined with 11kVbackup

24 N-1 22 N-1

98% 79%

Meets Vector security criteria

Constraint relieved by subtransmission circuit replacement

19 N-1 switched

115%

Meets Vector security criteria Meets Vector security criteria

24 N-1

93%

- N-1 switched

- -

-

Constraint relieved by the installation of thesecond transformer Constraint relieved by load transfer to Newmarket substation

- N

12 24

Drive

24 N-1 switched

110%

EastCoastRoad

Meets Vector security criteria

- N

-

-

EastTamaki

Meets Vector security criteria when combined with 11kVbackup

24 N-1 24 N-1 20 N-1

68% 47% 81%

24 24 20

Flatbush

Meets Vector security criteria Meets Vector security criteria

ForrestHill

Constraint relieved by load transfer to theCBD 22kVdistribution network Constraint relieved by transformer and subtransmission circuit replacements Constraint relieved by theHobsonvillePoint zonesubstation

Freemans Bay

22 N-1

98%

22

Glen Innes Greenhithe Greenmount Gulf Harbour

13 N-1 switched

119%

24

- N

-

-

Meets Vector security criteria Meets Vector security criteria

48 N-1

84%

48

- N

-

-

Hans

Meets Vector security criteria when combined with 11kVbackup

24 N-1 switched - N-1 switched 9 N-1 switched 15 N-1 switched

107%

24

Hauraki

Meets Vector security criteria

-

-

Helensville

Constraint relieved by transformer capacity upgrade

169% 118%

18 15 21 24 24 24 30

Henderson Valley

Meets Vector security criteria when combined with 11kVbackup

Highbrook Highbury

Meets Vector security criteria

21 N-1

-

44%

Constraint relieved by the installation of thesecond transformer

- N

-

Hillcrest

Meets Vector security criteria Meets Vector security criteria Meets Vector security criteria

24 N-1 24 N-1 30 N-1

84% 71% 46%

Hillsborough

Hobson 110/11kV