SECTION 2: PLANNING PROCESS
2019 Action #
2024 Status
Description
Status Comments/Explanation
Water and Sewer education materials on Town Website, including “What not to flush” and system reports.
This is an established capability of the town that is implemented on an ongoing basis.
PEA-7
Completed
Cary
P-5 P-6 P-8 P-9
Develop flood model for Symphony Lake Engineering evaluation of Tryon Road dam
Completed Incorporated into upper Swift Creek modeling effort.
Completed Completed Completed Completed Completed Completed Completed Completed Completed Completed
Conduct flood study on Town-owned lake/dam, including breach analysis
Triangle Regional Resiliency Partnership Culvert Replacement - Arbor Brook Culvert Replacement - Two Creeks
PP-1 PP-2
Project completed. Regional stormwater pond plus two GIS bioretention features built to retain/treat park SW plus existing street drainage.
NRP-1
Downtown Park
Completed
SP-1 SP-2
Infrastructure improvements on Summer Lakes Dr. Infrastructure improvements on Vincrest Ct
Completed Completed Completed Completed
Fuquay-Varina
P-5
Review and update of drought policy for water conservation
Completed Plan is updated every five years, originally adopted Feb 2024
Review and update requirements for mast arms to be installed over strain poles Review and update the 2014 Comprehensive Systemwide Parks, Recreation & Cultural Resources Master Plan for inclusion of hazard safety information at facilities
Complete; All projects inside Judd Pkwy required to have mast arms
P-6
Completed
P-7
Completed PRCR Master Plan updated in 2023
NRP-5 Install low flow/high efficiency toilets at new town hall
Completed Complete in 2019 Completed Complete in 2019 Completed Complete in 2019
S-1 S-2
Install a generator at the new town hall Install security cameras on new town hall
ES-8 Finalize implementation of new/updated radio communication equipment. Completed Completed Garner
UDO: Continue to provide stream and creek buffers, and floodplain and wetland protection. Develop for public dissemination building inspections brochures regarding high winds, water damage prevention, and tie downs for accessory structures. In the upcoming zoning and development ordinance update / re-write (UDO), look for ways discourage and steer high density residential and other at-risk populations (daycares, schools, and retirement facilities as examples)
P-2
Completed Completed with updates to UDO.
We do this annually - seasonal brochures based on weather threats
P-5
Completed
P-7
Completed Completed with updates to UDO.
Wake County, NC Multi-Jurisdictional Hazard Mitigation Plan
WSP June 2024 Page 21