SECTION 7: MITIGATION ACTION PLANS
Town of Fuquay-Varina
Potential Funding Sources
Hazard(s) Addressed
Relative Priority
Lead Agency/ Department
Implementation Schedule
Action #
Description
Goal Objective
Estimated Cost
2024 Status
Status Comments/Explanation
Natural Resource Protection
In-Progress – Carry Forward In-Progress – Carry Forward In-Progress – Carry Forward In-Progress – Carry Forward
Work with the U.S. Army Corps of Engineers on wetland protection.
Fuquay-Varina Planning
Budgeted Staff Time
Ongoing - Next 5 Years
Part of development and permit review process
NRP-1
4
1
Flood, Hurricane
Moderate
Annual Budget
Use Open Space Ordinance to protect wildlife habitat.
Fuquay-Varina Planning Fuquay-Varina Planning and Public Utilities
Budgeted Staff Time
Ongoing - Next 5 Years
Part of development and permit review process
NRP-2
4
1
All
Moderate
Annual Budget
Notify Wake County of any illegal stream dumping instances Enforce standards for tree protection and control of clear cutting (Town has received legislative authority to enact tree protection and control of clearcutting standards.)
Flood, Dam Failure, Hurricane
Budgeted Staff Time
Ongoing - Next 5 Years
Continued function of normal operation
NRP-3
3
1
Moderate
Annual Budget
Flood, Wildfire, Landslide
Fuquay-Varina Planning
Budgeted Staff Time
Ongoing - Next 5 Years
Part of development and permit review process
NRP-4
4
1
High
Annual Budget
Hazardous Materials Hazardous Materials
Fuquay-Varina Engineering Fuquay-Varina Public Utilities
Budgeted Staff Time Budgeted Staff Time
Ongoing - Next 5 Years Ongoing - Next 5 Years
NRP-5
Town Spill Response Plan
High
Annual Budget
New
N/A
Brighton Forest Wastewater Treatment Plant Decommissioning
NRP-6
High
BRIC
New
N/A
Structural Projects
The Town of Fuquay-Varina wishes to make modifications to the Crooked Creek Dam which was identified as a high hazard dam by NCDEQ. To pursue grant funding under FEMA BRIC this action was included as an amendment to the 2019 Wake County HMP. The Town of Fuquay-Varina wishes to make modifications to the Crooked Creek Dam which was identified as a high hazard dam by NCDEQ. To pursue grant funding under FEMA BRIC this action was included as an amendment to the 2019 Wake County HMP.
Local Funds, State Funds, Federal Funds, Other Sources
Geotechnical investigation to establish data for risk analysis and development of engineering designs/solutions
Town of Fuquay- Varina Engineering Department
To Be Determined
Carry Forward
S-1
3
3
Dam Failure
Moderate
2-5 Years
Local Funds, State Funds, Federal Funds, Other Sources
Implementing engineered design solutions to improve performance/safety of existing dam
Town of Fuquay- Varina Engineering Department
To Be Determined
Carry Forward
S-2
3
3
Dam Failure
Moderate
2-5 Years
Wake County, NC Multi-Jurisdictional Hazard Mitigation Plan
WSP June 2024 Page 312