SECTION 2: PLANNING PROCESS
2019 Action #
2024 Status
Description
Status Comments/Explanation
Obtain frequently updated, high-resolution aerial photography to assist with land use decisions, emergency response planning, and code enforcement. Working through the Triangle Water Supply Partnership, update the Water Resources Plan to ensure water supply is sufficient for Town's future needs. Working through the Triangle Water Supply Partnership, draft a Drought Management Plan to ensure water resources are properly managed during drought conditions. Working through the Triangle Water Supply Partnership, draft an Emergency Spill Response and Mitigation Plan to protect watersheds and other water resources from hazardous spills. Transition Wake County's sedimentation and erosion control permitting and monitoring to Town of Morrisville for better increased processing efficiency and faster incident response. Conduct a complete review and update to the Town's stormwater management program, which helps mitigate effects of stormwater runoff and flooding. Seek Federal, State, and County funding opportunities to purchase property located completely or partially in FEMA designated floodplains in order to mitigate potential property damage and protect natural resources. Construct Green Drive and Fairview Road Flood Reduction Drainage Project to mitigate potential flood hazards. Monitor the status of backup generators, communications and vehicles for all Morrisville owned critical public facilities. Install new generators for Town Hall and Police Station to ensure continuity of critical operations during a power outage. Construct new fire station in Morrisville in order to improve fire protection coverage and emergency response times. Update Town's Emergency Operations Plan to ensure best processes and procedures for the most likely and applicable emergency scenarios. Implement Wake County's Everbridge text alert system to notify citizens and Town staff of potential safety hazards or concerns. Utilize volunteer citizen committees, such as CERT or Public Safety Committee, to educate residents in preparing for natural hazards.
Good reference information of decision making and should continue to be a priority Original water supply plan was updated and completed in 2014. However, the item should be carried forward since the plan is currently being updated again.
P-5
Completed
P-6
Completed
P-7
Completed Completed in 2016
P-8
Completed Completed
P-9
Delete
Town decided to go in a different direction
P-10
Completed Town adopted a new stormwater management plan in 2023
PP-2
Completed Project Finished
SP-1
Completed Project was completed in 2021
ES-1
Completed Ongoing effort that needs to continue
ES-2
Completed One time project and has been completed
Initial project is complete, but it can migrate to the relocation of Fire Station 2
ES-3
Completed
ES-4
Completed Continuous project.
PEA-1
Completed Completed
PEA-3
Completed Completed
Rolesville
no completed or deleted actions
Wake County, NC Multi-Jurisdictional Hazard Mitigation Plan
WSP June 2024 Page 23