SECTION 7: MITIGATION ACTION PLANS
Town of Fuquay-Varina
Potential Funding Sources
Hazard(s) Addressed
Relative Priority
Lead Agency/ Department
Implementation Schedule
Action #
Description
Goal Objective
Estimated Cost
2024 Status
Status Comments/Explanation
Require delineation of Wake County Flood Hazard Soils, FEMA flood zones, and wetlands on final plats. Annual participation in Severe Weather Preparedness Week (March 3-9) via Weather Channel (social media campaign, newsletter, published materials) Annual participation in National Preparedness Month (September) Ready.gov (social media campaign, newsletter, published materials) Annual participation in Hurricane Prep Week (May 13-19) ReadyNC.gov (social media campaign, newsletter, published materials) Annual participation in Earthquake Awareness Month and National Earthquake Drill (February & October) Ready.gov (social media campaign, newsletter, published materials) Annual participation in National Dam Safety Awareness Day (May 31) Ready.gov (social media campaign, newsletter, published materials) Structured public education through social media, brochures, and flyers in critical facilities
In-Progress – Carry Forward
Flood, Dam Failure, Hurricane
Fuquay-Varina Planning
Budgeted Staff Time
Ongoing - Next 5 Years
Part of development and permit review process
PEA-6
Moderate
Annual Budget
3
2
Fuquay Varina Planning and Public Information
Budgeted Staff Time
Ongoing - Next 5 Years
PEA-7
1
1
All
High
Annual Budget
New
N/A
Fuquay Varina Planning and Public Information Fuquay Varina Planning and Public Information
Budgeted Staff Time
Ongoing - Next 5 Years
PEA-8
1
1
All
High
Annual Budget
New
N/A
Flood, Landslide, Hurricane
Budgeted Staff Time
Ongoing - Next 5 Years
PEA-9
1
1
High
Annual Budget
New
N/A
Fuquay Varina Planning and Public Information
Budgeted Staff Time
Ongoing - Next 5 Years
PEA-10
1
1
Earthquake
High
Annual Budget
New
N/A
Fuquay Varina Planning and Public Information Fuquay Varina Planning, Fire & Police, and Public Information
Budgeted Staff Time
Ongoing - Next 5 Years
PEA-11
1
1
Dam Failure
High
Annual Budget
New
N/A
Budgeted Staff Time
Ongoing - Next 5 Years
PEA-12
1
1
All
High
Annual Budget
New
N/A
Wake County, NC Multi-Jurisdictional Hazard Mitigation Plan
WSP June 2024 Page 316
Made with FlippingBook interactive PDF creator