SECTION 7: MITIGATION ACTION PLANS
Table 7.6 – Mitigation Action Plan, Town of Garner
Town of Garner
Potential Funding Sources
Hazard(s) Addressed
Relative Priority
Lead Agency/ Department
Estimated Cost
Implementation Schedule
2024 Status
Action #
Description
Goal Objective
Status Comments/Explanation
Prevention
The current UDO does not contain specific language to require or encourage low impact development; therefore, it is encouraged in practice rather than by regulation. With the expected addition of stormwater staff in the coming years, this will be incorporated into our overall stormwater program. Ongoing collaboration with the City of Raleigh and support of efforts to better the water supply system and search for regional supply solutions. The Town also participates in the Wake County One Water effort to address regional water supply. The Town's emergency preparedness plan follows the Wake County for routes. The Town's 2018 Transportation Plan does encourage and promote interconnectivity. Town has inventory of all structures in regulatory floodplains per the newest flood maps. Will continue expand inventory to contain structures in non- regulatory flood prone areas.
Evaluate the need for regulations to encourage use of low impact development site planning principles to help control stormwater volume impacts.
In-Progress – Carry Forward
Flood, Dam Failure, Hurricane
Garner Engineering and Planning
P-1
4
1
Moderate
Staff time
Local
2-3 years (2026)
Provide adequate water supply through storage and interconnection with other public water systems.
In-Progress – Carry Forward
City of Raleigh and Garner Engineering
P-2
3
2
Drought
Moderate
TBD
Local
2-3 years (2026)
Flood, Dam Failure, Earthquake, Hurricane, Severe Weather, Severe Winter Weather, Tornado, Hazardous Materials Incident,
Garner Transportation Plan – Continue to address disaster preparedness (evacuation) through road interconnectivity, paved roads, and widening of roads.
Improvement costs TBD on case-by-case basis
In-Progress – Carry Forward
Garner Planning and Public Works
Local, State, Federal
Ongoing - Next 5 Years
P-3
4
2
Moderate
Radiological Emergency, Terrorism
The Town will inventory all its structures located within or immediately adjacent to known flood hazard areas.
In-Progress – Carry Forward
Garner Planning and Engineering
Ongoing - Next 5 Years
P-4
2
2
Flood
Moderate
Staff time
Local
Property Protection
The Town has a service to respond to requests and questions from citizens regarding actions they may take to improve drainage, halt erosion, and to relocate, renovate or retrofit structures being flooded.
In-Progress – Carry Forward
Staff time should continue to be allocated to maintain this activity as part of normal Town operations.
Ongoing - Next 5 Years
PP-1
1
1
Flood
Moderate Garner Engineering
Staff time
Local, Private