Purchase of Open Space, Parks and Greenways – As part of new residential development, the Town collects dedicated open space and parkland, or fees- in-lieu of dedication to then purchase land in accordance with Town of Ordinance requirements and Comprehensive Planning documents. The Town also works with Wake County and other agencies to find other funding for open space acquisition. Once
Holly Springs Parks and Recreation
County & State Agencies
In-Progress – Carry Forward
More than 5 years
This is an ongoing goal to create open space, parks, and greenways in pace with the growth of the community
PP-4
4
2
Flood
Moderate
Land Cost
funds are obtained the Town will acquire land consistent with Land Use and Master Open Space Plans. Backup Power to Fire and Police Stations – The Town provides backup power to all fire and police stations. Fire Station 1 – backup power provided by a grant; backup power to Fire Station 2 and Fire Station 3 and Police Station provided by local funds. 3
Requires new facility. Cost unknown at this time.
In-Progress – Carry Forward
The new station is under construction, and we are finalizing contract with generator specifications. Will be completed by next update. The Town currently has an emergency generator to provide power to the Front Office of the Public Works Building during emergencies. The building personnel are getting relocated to a new facility. That facility is slated to be built in the next few years. Still in the planning phase and this new facility will include a generator. We have 3 new lift stations with 1 at a new fire station that are not built yet and do not have generators. Carry forward until stations are complete with generators. Will be deleted on next update. One existing pump station located in the SFHA is incompatible with newer lines and repeatedly failing, causing the release of wastewater into the floodplain and requiring costly response and cleanup. Construction of this Regional Pump Station will reduce wastewater flowing to this station and two others that flow to it, alleviating capacity concerns, reducing future flood damages, and reducing infrastructure upgrades in flood prone areas.
Holly Springs Public Safety
Local, Federal
PP-5
1
All
High
3-5 Years
In-Progress – Carry Forward
Holly Springs Public Works
To be determined
PP-6 Emergency Generator for Public Works Building
3
1
All
Moderate
Local
3-5 Years
In-Progress – Carry Forward
Holly Springs Public Utilities
To be determined
PP-7 Install additional Generators
3
1
All
High
Local
1 year
Build a Regional Pump Station to alleviate capacity concerns, reduce flood damages, and avoid infrastructure investments in older existing pump stations that are located in moderate and high flood risk areas.
Holly Springs Utilities and Infrastructure
Local, Federal
PP-8
3
2
All
High
$8 million
5 years
New
Natural Resource Protection
Holly Springs Utilities and Infrastructure
Restore bank stability and floodplain on Middle Creek.
Grant, Local
The Town is pursuing a Water Resources Development (WRD) grant to implement this project.
NRP-1
3
2
Flood
High
$250,000
2-3 years
New
Structural Projects
The Town is in the process of pursuing options to improve the existing spillway or create a secondary spillway. Per an agreement with NC Dam Safety, this will be completed within the next 5 years.
Holly Springs Engineering, Parks & Recreation
In-Progress – Carry Forward
Flood, Dam Failure
Over $100,000
This project is in design, it was delayed due to dispute between FEMA/Dam safety
S-1
3
2
High
Local
3-5 years