Wake County Hazard Mitigation Plan - Adopted 10-21-2024

SECTION 7: MITIGATION ACTION PLANS

Town of Holly Springs

Potential Funding Sources

Hazard(s) Addressed

Relative Priority

Lead Agency/ Department

Estimated Cost

Implementation Schedule

2024 Status

Action #

Description

Goal Objective

Status Comments/Explanation

Reservoirs/Retention/Detention Basins - The Town does not currently maintain any retention or detention basins. The Town does maintain Bass Lake Dam. The Town regularly provides maintenance of vegetation and minor erosion while providing visual inspections of the dam. If larger repairs are required, the Town will find appropriate means to resolve the problem. The Town also has a few small ponds located on existing parks. The Town maintains these ponds consistent with measures taken to maintain the Bass Lake Dam. Geotechnical investigation to establish data for risk analysis and development of engineering designs/solutions

Holly Springs Parks & Recreation

In-Progress – Carry Forward

Ongoing - Next 5 Years

Consistently and correctly maintains all ponds and dams. Ongoing project.

S-2

3

1

Flood

Moderate

Staff time

Local

The Town of Holly Springs plans to make modifications to the Bass Lake Dam which was identified as a high hazard dam by NCDEQ. To pursue potential funding under the FEMA High Hazard Dam Repair Program this action was included as an amendment to the 2019 Wake County HMP. The Town of Holly Springs plans to make modifications to the Bass Lake Dam which was identified as a high hazard dam by NCDEQ. To pursue potential funding under the FEMA High Hazard Dam Repair Program this action was included as an amendment to the 2019 Wake County HMP. The Town of Holly Springs plans to make modifications to the Bass Lake Dam which was identified as a high hazard dam by NCDEQ. To pursue potential funding under the FEMA High Hazard Dam Repair Program this action was included as an amendment to the 2019 Wake County HMP. The Town of Holly Springs plans to make modifications to the Bass Lake Dam which was identified as a high hazard dam by NCDEQ. To pursue potential funding under the FEMA High Hazard Dam Repair Program this action was included as an amendment to the 2019 Wake County HMP. The Town of Holly Springs plans to make modifications to the Bass Lake Dam which was identified as a high hazard dam by NCDEQ. To pursue potential funding under the FEMA High Hazard Dam Repair Program this action was included as an amendment to the 2019 Wake County HMP. The Town of Holly Springs plans to make modifications to the Bass Lake Dam which was identified as a high hazard dam by NCDEQ. To pursue potential funding under the FEMA High Hazard Dam Repair Program this action was included as an amendment to the 2019 Wake County HMP.

Local, State, Federal

Town of Holly Springs

To be determined

Carry Forward

S-3

3

3

Dam Failure Moderate

5 years

Local, State, Federal

Town of Holly Springs

To be determined

Carry Forward

S-4

Build upstream dam to reduce load on existing dam

3

3

Dam Failure Moderate

5 years

Local, State, Federal

Town of Holly Springs

To be determined

Carry Forward

S-5

Property Acquisition in inundation area(s) below dam 3

3

Dam Failure Moderate

5 years

Local, State, Federal

Town of Holly Springs

To be determined

Carry Forward

S-6

Raise crest of dam to increase storage capacity

3

3

Dam Failure Moderate

5 years

Local, State, Federal

Add additional spillways, widen or lower existing spillways to increase discharge capacity

Town of Holly Springs

To be determined

Carry Forward

S-7

3

3

Dam Failure Moderate

5 years

Local, State, Federal

Warning systems to alert downstream areas of potential dam failure

Town of Holly Springs

To be determined

Carry Forward

S-8

3

3

Dam Failure Moderate

5 years

Wake County, NC Multi-Jurisdictional Hazard Mitigation Plan

WSP June 2024 Page 321