Past Summer Activities: Paint crews abrasive blasted and primed Main Truss Spans (19-21) and Eastside Girder Spans (42-45) and Simple Beam Spans (46-51) and completed prescribed steel repairs . Current Activities & Upcoming Activities: All contract steel repairs are now completed, with 2 incidentally found repairs being worked on now . Intermediate Coat being applied to Span 16 with finish coat to follow as ambient conditions allow; platforms/access fencing to be dismantled .

Recent Progress

Work is 97% complete on the project; Time at 87% (Ahead)

Award Amount: $56,861,520.00 Paid to Date: $55,226,424.84