CAPITAL COMMITTEE PROJECT SUMMARY BB-3025-0000 - Cleaning and Painting Structural Steel at the Eastbound Bay Bridge (Phase 1)
PIN NUMBER CONTRACT NUMBER CONTRACT TITLE
2679 BB-3025-0000 Cleaning and Painting Structural Steel at the Eastbound Bay Bridge (Phase 1)
PROJECT SUMMARY
The work under this contract (Phase 1) includes providing all necessary labor, equipment, materials, and incidentals required to clean and paint structural steel on select eastbound portions of the William Preston Lane, Jr. Memorial (Bay) Bridge. The work will focus on deck truss spans T14 through T22, which have recently undergone deck replacement.
SCHEDULE
ADVERTISEMENT DATE
($)
11/20/2025
ANTICIPATED NOTICE TO PROCEED DATE
Advertised GOAL (%)
Proposed GOAL (%)
Apr-26
DURATION (CALENDER DAYS)
MBE PARTICIPATION
730
OVERALL MBE
18.00% 0.00% 0.00% 0.00% 0.00% 1.00%
18.01% 1.58% 0.65% 0.00% 15.78% 1.00%
AFRICAN AMERICAN ASIAN AMERICAN HISPANIC AMERICAN
WOMEN
VSBE
ENGINEER'S ESTIMATE (EE)
$48,601,932.00
BID RESULTS
BID AMOUNT ($)
% VARIANCE TO EE
BID PROTEST
YES
NO ☒
Blastech Enterprises
$45,941,500.00 $53,751,599.00 $58,886,250.00 $81,164,031.45
-5% 10% 21% 66%
Titan Industrial Services, Inc. Southern Road & Bridge LLC. Liberty Maintenance, Inc.
FUNDING SOURCE
100% TOLL REVENUE
Made with FlippingBook Digital Proposal Creator