Spray Park Feasibility Study
August 5, 2026
District of Hope – Engineering Department
Version 1.0
Flow-Through vs. Recirculation Spray Park Systems Feature Flow-Through
Recirculation
Water Use
Higher
Lower
Construction Cost
Lower
Higher
Maintenance
Lower
Higher
Water Treatment
Not Required
Required
Daily Testing
Minimal
Required
Power Requirements
Lower
Higher
Complexity
Lower
Higher
3.1. Flow-Through Systems Infrastructure Requirements Flow-through spray park systems use the municipal potable water supply to operate the park's spray features. Water pressure within the municipal system powers the spray equipment, and the water is used once before being discharged to the sanitary sewer system for treatment at the District's Pollution Control Centre (PCC). Flow-through systems are mechanically simpler to construct, operate, and maintain, resulting in lower capital costs and reduced operational requirements. Because fresh potable water is continuously supplied, water quality management is significantly simpler than with recirculation systems. This eliminates the need for daily water quality testing and could result in faster approvals from health authorities due to the lack of treatment facilities and simplicity of the design. Due to their simpler design, flow-through systems have fewer mechanical components to maintain and lower power requirements than recirculation systems. Permanent power supplied through a standard single-phase 15-amp (120-volt) electrical connection is typically sufficient to operate the control system. Some manufacturers also offer battery-powered control systems for installations where permanent power is not readily available; however, a permanent electrical connection is recommended wherever practical. While flow-through spray parks are constructed using simpler systems, they have a greater demand on the municipal potable water supply and sanitary sewer system. In practice, this means higher peak water usage during the dry summer months when the park is expected to operate, which also coincides with peak water conservation measures. Peak operating flows are expected to range between approximately 12–18 L/s (190–285 US gpm), depending on the final design and number of active spray features. These peak flows assume simultaneous operation of all spray fixtures but can be reduced through sequencing of spray fixtures in the electronic control system. As Hope sources potable water from groundwater wells, this water usage would result in increased duty cycles of well pumps and create an additional demand to the affected water storage reservoir. The discarded water from the facility would also have an increased demand on the sanitary sewer system, not only for conveyance in the gravity sewer mains, but also in pump station duty cycles and wastewater volumes being treated at the PCC. The connection of the spray park to the sewer system will, in essence, increase the infiltration and inflows (I&I) to the
Page 15
File: 5260-25
Made with FlippingBook - professional solution for displaying marketing and sales documents online