District of Hope Spray Park Feasibility Study

Explore potential locations, infrastructure needs, estimated costs and community benefits for a future spray park in Hope. This study supports future planning and Council decision-making, with final site selection subject to public engagement, detailed design and funding considerations.

A Technical and Community Assessment of Potential Spray Park Locations

August 5, 2026

Version 1.0

Prepared by:

Aaron Van Eyk, P.Eng., Director of Engineering

Edited by: Danielle Laporte, Communications System Analysis Advisor

325 Wallace Street, Hope, BC, V0X 1L0

Spray Park Feasibility Study

August 5, 2026

District of Hope – Engineering Department

Version 1.0

EXECUTIVE SUMMARY As Hope continues to invest in recreation, healthy living, and family-friendly amenities, community interest in developing a spray park has continued to grow. This feasibility study evaluates potential locations, servicing requirements, operational considerations, project costs, and overall viability to support future Council decision-making. Key Findings ✔ Three feasible candidate locations were evaluated. ✔ Existing municipal infrastructure can support future development. ✔ Spray parks provide significant recreational, tourism and community benefits. ✔ Infrastructure considerations can be addressed during future design. ✔ Further detailed design will refine costs and servicing requirements. Overall, the study concludes that the development of a spray park within Hope is technically feasible. While each location presents unique considerations, all candidate sites have the potential to support a successful community recreation facility subject to detailed design, funding, and Council direction.

Community Benefits ✔ Free summer recreation ✔ Supports healthy lifestyles ✔ Helps residents stay cool during extreme heat ✔ Inclusive play opportunities ✔ Tourism attraction ✔ Family gathering place ✔ Investment in parks and recreation

In response to growing community interest in the development of a spray park, the District of Hope undertook this feasibility study to evaluate the technical, operational, financial, and community considerations associated with constructing a new spray park. The study examines potential locations, servicing requirements, operational and maintenance needs, public health and safety considerations, community impacts, and estimated project costs. Two primary spray park system types were evaluated as part of this study: flow-through and recirculation systems. Flow-through systems use fresh potable water supplied directly from the municipal water system before discharging it to the sanitary sewer, resulting in a simpler and more cost-effective design. Recirculation systems continuously filter, disinfect, and reuse water, significantly reducing water consumption while requiring additional mechanical equipment, operational oversight, and higher capital investment. Three candidate locations were evaluated, including one site within Memorial Park and two potential locations at the 6th Avenue Fairgrounds. Each location offers existing recreational amenities, municipal servicing, and opportunities to support a future spray park. Preliminary servicing assessments indicate that all candidate locations can be connected to the District's

Page 2

File: 5260-25

Spray Park Feasibility Study

August 5, 2026

District of Hope – Engineering Department

Version 1.0

existing water and sanitary sewer infrastructure, with final servicing requirements to be confirmed during detailed design.

The study also evaluated the capacity of the District's broader municipal infrastructure, including the gravity sewer network, Coquihalla Lift Station, Pollution Control Centre, and potable water supply. While a future spray park would increase seasonal demands on these systems, preliminary review indicates that the existing infrastructure can accommodate anticipated flows. Additional engineering analysis will be required during detailed design to confirm long-term system capacity and identify any required upgrades. Operational requirements were reviewed for both mechanical system types. Routine maintenance is expected to include seasonal startup and winterization, daily inspections, cleaning, and minor repairs. Recirculation systems require additional responsibilities related to water treatment, filtration, and regulatory water quality monitoring, while flow-through systems have simpler operational requirements and lower long-term maintenance demands. Public health and safety considerations were also assessed. Appropriate design features (including slip-resistant surfacing, regulatory signage, effective drainage, and routine inspections) can help provide a safe and enjoyable environment for park users. Spray parks are regulated as public pools under Fraser Health, and the selected design will require regulatory review and operating approval prior to construction and operation. Beyond technical feasibility, a spray park has the potential to provide significant recreational and community benefits. It would create a free, inclusive outdoor recreation opportunity that supports healthy lifestyles, encourages family gathering, enhances accessibility, and contributes to Hope's parks and recreation network. Site-specific considerations, including parking, community events, accessibility, and compatibility with existing park uses, should continue to be evaluated during future planning. The candidate locations identified in this study are conceptual and intended to support feasibility analysis only. Final site selection will be subject to future Council direction, public engagement, detailed design, and funding considerations. Based on the findings of this study, the development of a spray park in the District of Hope is considered technically feasible. While each candidate location presents unique opportunities and design considerations, no significant technical barriers were identified that would prevent the project from moving forward.

Page 3

File: 5260-25

Spray Park Feasibility Study

August 5, 2026

District of Hope – Engineering Department

Version 1.0

TABLE OF CONTENTS 1. Background ...............................................................................................................................................6 2. Spray Park Candidate Locations...........................................................................................................6 2.1. Candidate Location 1 - Memorial Park......................................................................................7 2.2. Candidate Location 2 – 6th Avenue Fairgrounds................................................................. 10 2.2.1. Candidate Location 2A ..................................................................................................... 11 2.2.2. Candidate Location 2B ...................................................................................................... 13 3. Water and Sewer Infrastructure....................................................................................................... 14 3.1. Flow-Through Systems Infrastructure Requirements ......................................................... 15 3.2. Recirculation Systems Infrastructure Requirements ........................................................... 16 3.3. Municipal Water & Sewer Infrastructure Capacity.............................................................. 17 3.3.1. Gravity Sewer Network Capacity .................................................................................. 18 3.3.2. Coquihalla Lift Station Capacity ...................................................................................... 18 3.3.3. Contribution of Rainfall to Sanitary Sewer Flows....................................................... 18 3.3.4. Capacity of Potable Water Supply.................................................................................. 19 3.4. Conceptual Spray Pad Servicing Strategy ............................................................................... 20 3.4.1. Candidate Location 1 - Memorial Park Site Servicing Strategy................................ 20 3.4.2. Candidate Location 2A - 6th Avenue Site Servicing Strategy .................................. 22 3.4.3. Candidate Location 2B – 6th Avenue Site Servicing Strategy .................................. 23 4. Operations and Maintenance requirements ................................................................................... 24 4.1. Flow-Through Systems Operations and Maintenance ........................................................ 25 4.2. Recirculation Systems Operations and Maintenance .......................................................... 25 5. Water Quality and Public Safety ....................................................................................................... 26 5.1. Water Quality .............................................................................................................................. 26 5.2. Fraser Health Pool Permit ......................................................................................................... 27 5.3. User Safety Concerns................................................................................................................. 28 5.4. Vandalism concerns..................................................................................................................... 29 6. Community Benefits, Accessibility & Parking ................................................................................. 30 6.1. Community Benefits and Site Considerations ...................................................................... 30 6.1.1. Community Impacts & Benefits on Memorial Park..................................................... 31 6.1.2. Community Impact and Benefits on the 6th Avenue Fairgrounds .......................... 32 6.2. Accessibility & Inclusivity ........................................................................................................... 33 6.3. Parking............................................................................................................................................ 33 6.3.1. Parking at Memorial Park.................................................................................................. 33

Page 4

File: 5260-25

Spray Park Feasibility Study

August 5, 2026

District of Hope – Engineering Department

Version 1.0

6.3.2.

Parking at 6th Avenue Recreation Facilities ................................................................. 34

7. Project Costs & Funding Opportunities .......................................................................................... 36 7.1. Capital Costs ................................................................................................................................ 36 7.2. Operational & Maintenance Costs .......................................................................................... 37 7.2.1. Flow-Through System Operational & Maintenance Costs........................................ 38 7.2.2. Recirculation System Operational & Maintenance Costs.......................................... 39 7.3. Grants & Fundraising .................................................................................................................. 40 8. Recommendations ................................................................................................................................ 42

Page 5

File: 5260-25

Spray Park Feasibility Study

August 5, 2026

District of Hope – Engineering Department

Version 1.0

1. BACKGROUND

Interest in developing a community spray park has continued to grow in Hope for several years. Community members, families, and the Hope Splash Park Volunteer Committee have advocated for this amenity, recognizing its potential to enhance recreation, promote healthy living, and create a welcoming gathering place for residents and visitors. In response to this growing interest and the District of Hope's commitment to supporting recreation and young families, District staff undertook this feasibility study to better understand the technical requirements, potential challenges, and community benefits associated with developing a spray park. A spray park would provide a free, accessible outdoor recreation space for residents and visitors of all ages. It would create new opportunities for children and families to stay active, cool off during the summer months, and gather in a safe, inclusive public space. Beyond recreation, the facility has the potential to strengthen community connections, support local tourism, and complement Hope's existing parks and recreation network. This study is intended to inform District staff and Council on the overall feasibility of developing a community spray park in Hope. It provides information on candidate locations, municipal servicing requirements, operational and maintenance considerations, and estimated project costs. Additional factors, including public safety, community impacts, accessibility, and inclusivity, are also evaluated to support informed, equitable, and sustainable decision-making. If advanced, the project has the potential to become a lasting community asset that supports the District's vision for recreation, healthy living, tourism, and an inclusive, family-friendly community. 2. SPRAY PARK CANDIDATE LOCATIONS The locations presented in this report are conceptual and were selected for the purposes of evaluating technical feasibility, servicing requirements, community impacts, and overall suitability. They should not be interpreted as the only potential locations for a future spray park. Additional sites or refinements to the conceptual layouts may be considered through future Council direction, public engagement, and detailed design.

Existing Amenities

Utilities Nearby

Recreation Context

Candidate Location

Parking

Memorial Park

Moderate

Downtown

✓

✓

6th Avenue Site 2A

Excellent

Recreation Hub

✓

✓

6th Avenue Site 2B

Excellent

Recreation Hub

✓

✓

Two candidate locations were evaluated as part of this feasibility study: Memorial Park, located adjacent to the District of Hope Municipal Hall, and the 6th Avenue Fairgrounds, located adjacent to the Hope Recreation Centre. Within the 6th Avenue Fairgrounds, two potential spray park locations (Sites 2A and 2B) were considered. An overview of the candidate locations is provided in Figure 1.

Page 6

File: 5260-25

Spray Park Feasibility Study

August 5, 2026

District of Hope – Engineering Department

Version 1.0

N

Figure 1. Candidate Spray Park Locations Evaluated in this Study

Each candidate location was evaluated using consistent criteria, including existing amenities, available space, municipal servicing, community impacts, accessibility, and parking. Together, these factors help identify the opportunities and considerations associated with each site.

Site

Key Strengths

Memorial Park

Downtown location, existing playground, washrooms, picnic areas

Site 2A

Large open area, excellent parking, recreation hub

Site 2B

Close to washrooms, visible location, easier accessibility

2.1. Candidate Location 1 - Memorial Park Memorial Park has long been identified as a potential location for a community spray park due to its central downtown location, established park amenities, and role as one of Hope's most popular gathering spaces. The proposed spray park location is adjacent to the existing playground, creating opportunities to complement existing recreational amenities while making use of the surrounding picnic areas and washroom facilities. Although the site offers many advantages, it must also accommodate existing community events and seasonal parking demands. These considerations are discussed in greater detail in the Community Benefits section of this report. An overview of the proposed location is shown in Figure 2. The suitability of Memorial Park for a future spray park is also supported by previous District planning initiatives. The Hope Downtown Action Plan (2023), under Section 4.4 Enhance the Heart – Memorial Park , identifies the creation of a spray park adjacent to the existing children's playground as one of the key strategies to strengthen Memorial Park as the heart of downtown.

Page 7

File: 5260-25

Spray Park Feasibility Study

August 5, 2026

District of Hope – Engineering Department

Version 1.0

The Action Plan recognizes the park as a valued destination for residents and visitors and recommends additional recreational amenities that encourage year-round community use. The proposed spray park location identified in this feasibility study aligns with that long-term strategic direction while building upon the park's existing role as central gathering place.

Memorial Park Highlights ✔ Downtown location ✔ Existing playground ✔ Existing washrooms ✔ Picnic facilities ✔ Mature park setting ✔ Walkable from nearby neighbourhoods

Figure 2: Conceptual Spray Park Location within Memorial Park

The proposed location within Memorial Park provides ample space to accommodate a moderately sized spray park while complementing the park's existing recreational amenities. Approximately 600 m² (6,460 sq. ft.) of space is available, with additional room for seating, picnic areas, landscaping, and other park amenities if desired. Locating the spray park adjacent to the existing playground creates an opportunity to establish a larger, multi-use family

Page 8

File: 5260-25

Spray Park Feasibility Study

August 5, 2026

District of Hope – Engineering Department

Version 1.0

recreation destination where children of different ages can enjoy complementary play experiences within a single park visit.

The site's proximity to existing washroom facilities reduces the need for additional supporting infrastructure and enhances convenience for park users. These facilities are in good condition, are regularly maintained by District staff, and support the site's suitability for a future spray park. Figure 3 below identifies the proposed spray park location adjacent to the existing playground.

Figure 3: Photograph of Proposed Location for a Spray Park within Memorial Park

While Memorial Park offers many advantages (including its central location, established amenities, and existing playground), several site-specific considerations should be addressed during detailed design. The park's mature tree canopy contributes significantly to its character while providing valuable shade during the summer months. Design should seek to preserve mature trees where possible while minimizing the potential impacts of falling leaves, conifer needles, and branches on spray park infrastructure and maintenance requirements. Parking demand may also increase during peak summer periods and community events; however, this should be considered alongside the site's excellent walkability and central downtown location. As Memorial Park regularly hosts community events, the final spray park layout should maintain flexibility for existing park uses while enhancing the park's long-term recreational value.

Memorial Park Considerations ✔ Preserve mature trees where possible ✔ Evaluate parking during peak periods ✔ Maintain flexibility for community events ✔ Design drainage to reduce maintenance

Page 9

File: 5260-25

Spray Park Feasibility Study

August 5, 2026

District of Hope – Engineering Department

Version 1.0

Overall, Memorial Park remains a strong candidate location. The identified considerations are primarily related to site planning and park operations and can be further evaluated during detailed design. Candidate Location 2 – 6th Avenue Fairgrounds The 6th Avenue Fairgrounds represent Hope's primary recreation hub and provides a strong opportunity for the development of a future spray park. The surrounding area includes the Hope Recreation Centre, skate park, bike park, baseball diamonds, campground, and other recreational amenities, creating an established destination for residents and visitors. The site offers ample open space, existing municipal servicing, and excellent parking, making it well suited to accommodate a spray park while complementing the surrounding recreation facilities. Existing washroom facilities, located north of the Hope Curling Club, are maintained by District staff; however, they are a relatively small, aging facility, and do not currently meet modern accessibility standards. 2.2. Due to the size of the 6th Avenue Fairgrounds, two potential spray park locations were evaluated. Candidate Location 2A is situated adjacent to the existing skate park, immediately north of the conference centre, while Candidate Location 2B is located northeast of the Hope Curling Club within the northern portion of the existing off-leash dog park. Both locations offer sufficient space to accommodate a future spray park and are evaluated independently throughout this report.

Page 10

File: 5260-25

Spray Park Feasibility Study

August 5, 2026

District of Hope – Engineering Department

Version 1.0

2.2.1. Candidate Location 2A With more than 1,300 m² (14,000 sq. ft.) of available space, this site offers considerable flexibility for future design, including seating areas, landscaping, shade structures, and potential future expansion. The conceptual location for site 2A is shown below in Figure 4.

Figure 4: Conceptual Spray Park Location at the 6th Avenue Fairgrounds Adjacent to the Skate Park

While this site offers significant advantages, including abundant open space and excellent parking, several design considerations should be addressed. The site has limited natural shade, reduced visibility (compared to Site 2B) and is located farther from the existing washroom facilities north of the Hope Curling Club. Users would be required to cross the roadway to access the washrooms; therefore, a marked pedestrian crossing should be considered part of any future spray park development. In addition, the existing washroom facilities are relatively small and do not meet current accessibility standards, which may result in future upgrades or replacement being considered.

Page 11

File: 5260-25

Spray Park Feasibility Study

August 5, 2026

District of Hope – Engineering Department

Version 1.0

Figure 5: Candidate Location 2A Adjacent to the Skate Park and Conference Center.

As shown in Figure 5, Candidate Location 2A provides a largely unobstructed site with minimal impacts on existing park uses. The available space offers considerable flexibility for the future layout of spray features, seating, landscaping, and supporting amenities. Additional details regarding municipal servicing and community considerations are discussed in the following sections of this report.

Page 12

File: 5260-25

Spray Park Feasibility Study

August 5, 2026

District of Hope – Engineering Department

Version 1.0

2.2.2. Candidate Location 2B Candidate Location 2B is situated northeast of the Hope Curling Club, occupying the northern portion of the existing off-leash dog park. This location offers good visibility within the recreation complex and is located closer to existing washroom facilities than Candidate Location 2A. A conceptual layout of the proposed spray park location is shown in Figure 6 below.

Figure 6: Candidate Location 2B Adjacent to the Hope Curling Club

This location provides approximately 800 m² (8,600 sq. ft.) of available space for a future spray park. Compared to Candidate Location 2A, the site offers increased visibility, closer proximity to existing washroom facilities, and a smaller elevation change, simplifying accessibility planning and site design. Figure 7 shows the location of Candidate location 2B adjacent to the ball diamonds.

Page 13

File: 5260-25

Spray Park Feasibility Study

August 5, 2026

District of Hope – Engineering Department

Version 1.0

Figure 7: Photograph of Candidate Location 2B Adjacent to the Dog Park and Ball Diamonds

The primary consideration associated with this location is the potential impact on the existing off-leash dog park. The close proximity of a children’s play area and dog park may reduce user comfort and create potential conflicts between recreational activities. Additional considerations include the age and limited accessibility of the nearby washroom facilities, as well as the potential for foul balls from the adjacent baseball diamonds to enter the spray park area. These considerations, together with municipal servicing requirements, are discussed in greater detail in the following sections of this report. 3. WATER AND SEWER INFRASTRUCTURE To support a future spray park, connections to the District's municipal water supply and sanitary sewer system will be required. All candidate sites evaluated in this study are located in close proximity to existing municipal infrastructure, making water and sewer servicing technically feasible. Two primary mechanical system types are commonly used for spray parks: flow-through and recirculation systems. Each offers distinct advantages and operational considerations. To better understand available system options and servicing requirements, District staff consulted with two spray park manufacturers—Vortex (PlayQuest) and Waterplay (Makr Group). Both manufacturers are based out of Western Canada and have extensive experience designing installations throughout British Columbia. These manufacturers are capable of providing either system type to suit site-specific requirements.

Page 14

File: 5260-25

Spray Park Feasibility Study

August 5, 2026

District of Hope – Engineering Department

Version 1.0

Flow-Through vs. Recirculation Spray Park Systems Feature Flow-Through

Recirculation

Water Use

Higher

Lower

Construction Cost

Lower

Higher

Maintenance

Lower

Higher

Water Treatment

Not Required

Required

Daily Testing

Minimal

Required

Power Requirements

Lower

Higher

Complexity

Lower

Higher

3.1. Flow-Through Systems Infrastructure Requirements Flow-through spray park systems use the municipal potable water supply to operate the park's spray features. Water pressure within the municipal system powers the spray equipment, and the water is used once before being discharged to the sanitary sewer system for treatment at the District's Pollution Control Centre (PCC). Flow-through systems are mechanically simpler to construct, operate, and maintain, resulting in lower capital costs and reduced operational requirements. Because fresh potable water is continuously supplied, water quality management is significantly simpler than with recirculation systems. This eliminates the need for daily water quality testing and could result in faster approvals from health authorities due to the lack of treatment facilities and simplicity of the design. Due to their simpler design, flow-through systems have fewer mechanical components to maintain and lower power requirements than recirculation systems. Permanent power supplied through a standard single-phase 15-amp (120-volt) electrical connection is typically sufficient to operate the control system. Some manufacturers also offer battery-powered control systems for installations where permanent power is not readily available; however, a permanent electrical connection is recommended wherever practical. While flow-through spray parks are constructed using simpler systems, they have a greater demand on the municipal potable water supply and sanitary sewer system. In practice, this means higher peak water usage during the dry summer months when the park is expected to operate, which also coincides with peak water conservation measures. Peak operating flows are expected to range between approximately 12–18 L/s (190–285 US gpm), depending on the final design and number of active spray features. These peak flows assume simultaneous operation of all spray fixtures but can be reduced through sequencing of spray fixtures in the electronic control system. As Hope sources potable water from groundwater wells, this water usage would result in increased duty cycles of well pumps and create an additional demand to the affected water storage reservoir. The discarded water from the facility would also have an increased demand on the sanitary sewer system, not only for conveyance in the gravity sewer mains, but also in pump station duty cycles and wastewater volumes being treated at the PCC. The connection of the spray park to the sewer system will, in essence, increase the infiltration and inflows (I&I) to the

Page 15

File: 5260-25

Spray Park Feasibility Study

August 5, 2026

District of Hope – Engineering Department

Version 1.0

sanitary sewer from the resulting precipitation entering the spray park drains during after-hours and in the off season.

An innovative approach recently implemented by the City of Abbotsford uses an adjustable diversion structure that directs precipitation runoff to the storm drainage system during the off-season while routing spray park water to the sanitary sewer during operation. A similar approach could be considered during detailed design. Key Considerations: Flow-Through Systems ✔ Lower construction and operating costs ✔ Simpler to operate and maintain ✔ Reduced regulatory and water quality monitoring requirements ✖ Higher potable water consumption ✖ Greater demand on municipal sewer infrastructure Recirculation Systems Infrastructure Requirements A recirculation system is an alternative spray park system that significantly reduces water consumption by continuously collecting, treating, and reusing water. These systems rely on additional mechanical equipment to filter, disinfect, monitor, and pump water before it is recirculated through the park's spray features. 3.2. Although recirculation systems require periodic top ups to replace water lost through evaporation and splash out, they significantly reduce overall demand on the municipal potable water supply and sanitary sewer system compared to flow-through systems. Recirculation systems also provide greater operational control through more advanced automation. Depending on the manufacturer, operators may have enhanced capabilities for system monitoring, performance adjustments, diagnostics, and future upgrades. While the recirculation pump and controller systems offer additional flexibility to park operators, the power requirements for these systems are higher than flow-through type systems. These systems typically require split-phase or three-phase electrical service connections and may draw a peak current up to approximately 50 amps, depending on the final system design. The primary operational consideration associated with recirculation systems is the increased complexity required to safely treat and reuse water. Water must be continuously filtered, disinfected, and chemically treated to meet applicable health standards. As a result, operational staff are required to perform routine water quality testing each day the facility is in operation, with additional testing following contamination events involving fecal matter, urine, pets, or wildlife. The additional treatment equipment, pumps, filtration systems, chemical storage, and control infrastructure increase both initial construction costs and long-term operating expenses. Higher power consumption, chemical usage, routine maintenance, and more complex repairs all contribute to increased lifecycle costs compared to flow-through systems.

Page 16

File: 5260-25

Spray Park Feasibility Study

August 5, 2026

District of Hope – Engineering Department

Version 1.0

Key Considerations: Recirculation Systems ✔ Significantly reduced water consumption

✔ Lower demand on municipal water and sewer systems ✔ Greater operational flexibility and system controls ✖ Higher construction costs ✖ More complex operation, maintenance, and regulatory requirements

Flow-Through vs. Recirculation Spray Park Systems Feature Flow-Through System

Recirculation System

Higher – potable water is used once before being discharged to the sanitary sewer.

Lower – water is continuously filtered, treated, and reused, with only periodic top-ups required. Higher capital cost due to pumps, filtration, treatment, and control equipment. Higher annual operating costs for treatment chemicals, testing, maintenance, and electricity. More complex operation requiring specialized maintenance and equipment servicing. Daily water quality testing and ongoing monitoring required to meet health regulations. Higher; typically requires split-phase or three-phase electrical service. Conserves water but requires chemical treatment and additional energy use.

Water Use

Lower capital cost due to simpler mechanical systems.

Construction Cost

Lower annual operating and maintenance costs.

Operating Cost

Simpler operation with fewer mechanical components.

Maintenance

Water Quality Testing

Minimal, as fresh potable water is continuously supplied.

Power Requirements

Low; typically a standard 120V electrical connection. Greater potable water consumption and higher sanitary sewer discharge volumes.

Environmental Considerations

Operational Complexity

Low

Moderate to High

3.3. Municipal Water & Sewer Infrastructure Capacity Although a spray park would increase demand on the District's water and sanitary sewer systems, preliminary review indicates that existing municipal infrastructure can accommodate the anticipated flows. Additional engineering analysis will be required during detailed design to confirm system capacity and identify any required upgrades.

Page 17

File: 5260-25

Spray Park Feasibility Study

August 5, 2026

District of Hope – Engineering Department

Version 1.0

Key Findings ✔ Existing municipal water and sewer infrastructure can support a future spray park. ✔ Additional engineering analysis will be required during detailed design to confirm long-term system capacity. ✔ Seasonal spray park operations reduce impacts because peak demand occurs during the summer rather than during wet-weather sewer events. Gravity Sewer Network Capacity Regarding sanitary sewer servicing, there is generally sufficient capacity within the gravity sewar system to accommodate additional flows from the candidate sites. Downstream of Candidate Location 2, the District's Sanitary Master Plan identifies two isolated sections of the gravity sewer network along Coquihalla Street, between 4 th and 5 th avenues, that are approaching capacity. The 200mm diameter sewers in this area are at approximately 90% capacity in existing conditions, and in future growth scenarios these mains will reach their available capacity. The addition of flows from spray park operations could approach or exceed available capacity during peak operating conditions, but a more detailed analysis of the capacity of this system should be conducted to determine the risk of surcharging the main. Peak spray park usage is expected to occur during summer afternoons, whereas peak sanitary sewer flows typically occur during wet-weather events and during the morning and evening hours. Because these peak demands are unlikely to occur simultaneously, the overall impact on sewer capacity may be reduced. Additional analysis will be required during detailed design to confirm this assumption. 3.3.1. 3.3.2. Coquihalla Lift Station Capacity Regardless of the selected location, wastewater generated by the spray park would ultimately be conveyed through the Coquihalla Lift Station. The Coquihalla Lift Station is a critical infrastructure, conveying wastewater from the downtown and Kawkawa Lake areas to the District's Pollution Control Centre (PCC). This pump station is estimated to have a total capacity of 110L/s according to the District’s Sanitary Master Plan. Existing flows entering this pump station are estimated to be approximately 80L/s at the Coquihalla pump station, at 73% of total capacity. Future growth scenarios have estimated an ultimate demand of 97 L/s, reaching 88% of capacity. Peak flows from a spray park, particularly a flow-through system, could increase flows to near or above the station's theoretical capacity during peak spray park operation. Because peak spray park usage is expected to occur during summer conditions rather than peak wet-weather events, these peak demands may not occur simultaneously. This assumption should be confirmed during a detailed design. Contribution of Rainfall to Sanitary Sewer Flows Seasonal operating patterns reduce one of the primary concerns associated with additional sanitary sewer flows. Typical sewer flows reach their peak during the wettest months of the year, when unintended infiltration and inflows enter the sanitary sewer network due to elevated groundwater levels and heavy rainfall events. Sanitary sewer design is typically governed by these Peak Wet Weather Flow (PWWF) conditions which consider the additional flow observed in sewer system following extended periods of wet weather. In Hope, the PWWF is frequently over twice the Average Dry Weather Flow (ADWF) which is more reflective of the day-to-day demands on the sewer system. 3.3.3.

Page 18

File: 5260-25

Spray Park Feasibility Study

August 5, 2026

District of Hope – Engineering Department

Version 1.0

A unique advantage of spray park flows is their seasonal nature. Peak wet weather conditions rarely occur during the summer months when spray park usage is expected to be highest. As a result, peak rainfall inflows and peak spray park flows are unlikely to occur simultaneously, reducing the potential impact on sanitary sewer capacity. This assumption should be confirmed during a detailed design of the selected site. To further reduce impacts on the sanitary sewer system, a secondary connection to the stormwater drainage system could be incorporated into the spray park design. While this connection would not be used during normal spray park operation, it could direct precipitation runoff to the storm system during the off-season, reducing unnecessary contributions to the sanitary sewer and the District's Pollution Control Centre. A simple valve and wye assembly would allow Operations staff to redirect drainage as part of the annual winterization process. This approach should be considered during preliminary design. 3.3.4. Capacity of Potable Water Supply Both candidate sites explored in this study would draw from the District’s 87m water zone. A spray park would increase overall demand within the District's 87m water zone, resulting in modest additional reservoir drawdown during operation and a temporary reduction in available fire flows nearby. This would present itself as an additional reservoir drawdown during park operations as well as a possible reduction of available flows for fire protection in the immediate vicinity of the splash pad. Available flow in the 87m water systems varies by location but are generally acceptable for residential land-usage. Available flows in the vicinity of the Memorial Park exceed 80L/s and exceed 110L/s at 6th Avenue according to the Water Master Plan. These available fire flows do fall short of requirements for commercial and industrial land usage, which ideally require more than 150L/s for full fire protection. Flow utilized by the splash pad during operating hours could directly reduce this available fire flow by up to 18L/s in the case of a large flow-through system. Given the existing nature of these flow deficiencies, the intermittent and seasonal nature of the spray park and the availability of alternative solutions to reduce fire flow requirements, these constraints to water conveyance could be deemed acceptable. Despite these drawbacks, the 87m water zone is relatively robust, as it is supplied by three operational wellheads (wells #1, #2 and #3), and a 1587m 3 reservoir volume with sufficient head pressure supplying the zone. The wells themselves are over 50 years old and will require eventual replacement, but the replacement of pumps at well #1 and #2 in the past 10 years have extended their operational lifespans, reducing the risk to the water system. The anticipated annual water demand of approximately 12,000m³ represents roughly 1.5% of the existing annual water consumption within the 87m water zone. The Water Master plan has indicated that a small deficiency of 400m 3 exists in the 87m water zone under the design scenario of a sustained 150L/s fire flow for 2 hours. This deficiency assumes simultaneous occurrence of maximum daily water usage plus fire flows. While this is the ideal design scenario, very few locations in the 87m water zone are even capable of delivering this theoretical 150L/s fire flow requirement in the existing condition without adversely impacting pressure in the water system. Future improvements to the cross-

Page 19

File: 5260-25

Spray Park Feasibility Study

August 5, 2026

District of Hope – Engineering Department

Version 1.0

connection between the 87m and 138m water zones will reduce these impacts as water can flow between the different zones during limited periods of extreme water usage.

Infrastructure

Assessment

Gravity Sewer

✔ Generally adequate; localized capacity review recommended

Coquihalla Lift Station

✔ Additional analysis required during detailed design

Water Supply ✔ Existing system capable of supporting projected demand Seasonal Demand ✔ Peak spray park use occurs outside peak sewer design events

3.4. Conceptual Spray Pad Servicing Strategy Both candidate locations have convenient access to existing municipal water and sanitary sewer infrastructure, making municipal servicing technically feasible. The final servicing requirements will depend on the selected site, spray park size, and mechanical system type. The conceptual servicing strategies presented below illustrate one potential approach and are intended to guide future detailed design. Note: Conceptual Only The servicing layouts shown in this section are preliminary and are intended to demonstrate technical feasibility only. Final utility alignments, pipe sizes, and construction methods will be confirmed during detailed design. 3.4.1. Candidate Location 1 - Memorial Park Site Servicing Strategy Water and sewer servicing for the proposed Memorial Park spray park would most likely originate between the existing bus stop and the Japanese Friendship Garden. This location provides access to municipal water, sanitary sewer, and—if incorporated into the final design— storm drainage infrastructure. Servicing the site adjacent to the existing playground would require excavation and restoration of 3 rd Avenue and the sidewalk passing through Memorial Park. A brief overview of the existing municipal water systems is shown in Figure 8.

Page 20

File: 5260-25

Spray Park Feasibility Study

August 5, 2026

District of Hope – Engineering Department

Version 1.0

Figure 8: Conceptual Servicing Strategy for Spray Park in Memorial Park

The water connection could be sourced from the 150 mm diameter watermain along Commission Street. The proposed water connection would tie into the 150 mm watermain along Commission Street, which transitions to a 50 mm diameter crossing beneath 3rd Avenue. Typical spray park services require a 50 mm connection or smaller; however, should detailed design indicate a larger service is required, this section of watermain could be upgraded accordingly. The sanitary sewer connection can be made to the existing sanitary sewer infrastructure at the intersection of 3 rd Avenue and Commission Street. To avoid disturbing the existing 200 mm asbestos concrete sewer main, it is recommended that the connection be made directly at the existing sanitary manhole. If the optional drainage service is pursued, to provide off-season drainage to the pad, the connection can be made in the same area as the water and sewer connections. If an optional storm drainage connection is included for off-season drainage, it is also recommended that the connection be made directly at the existing manhole to avoid tapping the asbestos concrete pipe.

Overall, Memorial Park can be serviced using existing municipal water and sewer infrastructure, with no significant servicing constraints identified at the feasibility stage. Final utility alignments,

Page 21

File: 5260-25

Spray Park Feasibility Study

August 5, 2026

District of Hope – Engineering Department

Version 1.0

pipe sizing, and construction requirements can be refined during detailed design based on the selected spray park configuration. 3.4.2. Candidate Location 2A - 6th Ave nue Site Servicing Strategy Because of the size of the 6th Avenue property, servicing requirements vary depending on the selected spray park location. Separate conceptual servicing strategies have therefore been prepared for Candidate Locations 2A and 2B. Candidate location 2A, adjacent to the existing skate park, can be serviced through the existing 200 mm water main beneath the parking lot beside the conference center. The existing 200 mm watermain adjacent to the conference centre provides sufficient capacity to service a future spray park. The sanitary sewer connection to the pad could be made with a short service connection to the 200 mm asbestos concrete sewer in the lane immediately adjacent to the site, located south of Hudson Bay Street. Depending on the final alignment, installation of an additional manhole may be recommended to avoid tapping directly into the existing asbestos concrete sewer main. A conceptual servicing plan is shown in Figure 9 below.

Figure 9: Conceptual Servicing Strategy for Candidate Location 2A at 6th Avenue Fairgrounds

The optional drainage connection could likely be made into the parking lot area, near the proposed water service connection, but minimal information is currently available for the

Page 22

File: 5260-25

Spray Park Feasibility Study

August 5, 2026

District of Hope – Engineering Department

Version 1.0

drainage infrastructure within the conference center parking lot. The length of water and drainage connections for this location would be the longest of all candidate sites but has the shortest sewer connection length. Servicing this site would require excavation and restoration of the parking lot to accommodate the construction. Overall, Candidate Location 2A can be serviced using existing municipal infrastructure, with no significant servicing constraints identified at the feasibility stage. The site's proximity to existing water and sewer mains provides a practical servicing solution, while final utility alignments and construction requirements can be confirmed during detailed design. 3.4.3. Candidate Location 2B – 6th Ave nue Site Servicing Strategy Candidate Location 2B can be serviced using existing municipal water and sanitary sewer infrastructure located adjacent to the Hope Curling Club. The conceptual servicing strategy shown below demonstrates one potential servicing arrangement and is intended to guide future detailed design. This location would provide the shortest connection lengths of all the candidate sites. An existing 50mm diameter watermain branches off the 200 mm diameter watermain in the recreation center parking lot to service the existing washroom facility. While the 50 mm main is immediately adjacent to the proposed location, either of these two watermains could be easily connected to, depending on the actual required water demand. The sanitary sewer connection would tie into the existing municipal sewer system located adjacent to the site. Like the other sewer connections, it is recommended to make connection at the manhole rather than connecting directly into the asbestos concrete sewer main. A conceptual servicing plan is shown in Figure 10.

Page 23

File: 5260-25

Spray Park Feasibility Study

August 5, 2026

District of Hope – Engineering Department

Version 1.0

Figure 10: Conceptual Servicing Strategy of Candidate Location 2B at 6th Avenue Fairgrounds

Should an off-season drainage connection be incorporated into the final design, it could be routed to the municipal drainage system using a manually operated diversion valve but limited information is available on the drainage infrastructure in the parking lot adjacent to the site. The servicing to this location would likely require the shortest overall service connection lengths of all the candidate locations and additionally would require the least amount of disturbance to paved areas, minimizing pavement restoration costs. Overall, Candidate Location 2B can be serviced using existing municipal infrastructure with no significant servicing constraints identified at the feasibility stage. Final utility alignments and construction requirements will be confirmed during detailed design. 4. OPERATIONS AND MAINTENANCE REQUIREMENTS Once constructed, a spray park would require routine seasonal operation and maintenance similar to other municipal recreation assets. The level of maintenance depends largely on the mechanical system selected, with flow-through systems requiring simpler daily operation and recirculation systems requiring additional water treatment and monitoring.

Page 24

File: 5260-25

Spray Park Feasibility Study

August 5, 2026

District of Hope – Engineering Department

Version 1.0

4.1. Flow-Through Systems Operations and Maintenance Flow-through systems use municipal potable water pressure to supply the spray park features. Although these systems place a greater day-to-day demand on municipal water and sanitary sewer infrastructure, the spray park itself relies on relatively simple mechanical equipment. This simplicity reduces the amount of routine maintenance and staff time required to operate the facility.

Typical Flow-Through Maintenance ✔ Seasonal Spring startup ✔ Daily visual inspection ✔ Routine cleaning and debris removal ✔ Minor repairs as required ✔ Fall winterization

Flow-through systems still require electronic controllers, push-button activators, and control valves to operate the spray features; meaning periodic maintenance and occasional repairs will be required. However, the overall scale of maintenance is relatively limited. Because fresh potable water is supplied directly from the municipal system, onsite water treatment and continuous water quality testing are not required. Operations staff will complete seasonal startup and winterization procedures at the beginning and end of each operating season. During the operating season, a daily pre-opening inspection is required to comply with Fraser Health requirements and identify any hazards, debris, or maintenance issues before the facility opens to the public. Day-to-day operation of the spray features is managed automatically through the electronic control system and push-button activators, requiring minimal staff intervention during normal operation. Overall, flow-through systems have relatively straightforward operational requirements and can be maintained using routine municipal operations practices. Their mechanical simplicity results in lower labour demands and reduced long-term maintenance requirements compared to recirculation systems. Recirculation Systems Operations and Maintenance Recirculation systems require additional mechanical equipment to operate the spray park, resulting in increased operational and maintenance requirements compared to flow-through systems. Additional costs include electricity for pumps, treatment chemicals, routine water quality testing, and ongoing maintenance of filtration and mechanical equipment. The increased complexity of components such as pumps, variable frequency drives, and chemical dosing systems may also require specialized contractors for some maintenance and repair activities. 4.2. Recirculation systems significantly reduce demand on the municipal water supply and sanitary sewer system by continuously treating and reusing water. These reductions in water consumption can help offset the increased operational complexity while supporting water conservation objectives. The advanced control systems also provide operators with greater flexibility to monitor, adjust, and optimize system performance.

Page 25

File: 5260-25

Page 1 Page 2 Page 3 Page 4 Page 5 Page 6 Page 7 Page 8 Page 9 Page 10 Page 11 Page 12 Page 13 Page 14 Page 15 Page 16 Page 17 Page 18 Page 19 Page 20 Page 21 Page 22 Page 23 Page 24 Page 25 Page 26 Page 27 Page 28 Page 29 Page 30 Page 31 Page 32 Page 33 Page 34 Page 35 Page 36 Page 37 Page 38 Page 39 Page 40 Page 41 Page 42 Page 43 Page 44