Spray Park Feasibility Study
August 5, 2026
District of Hope – Engineering Department
Version 1.0
recirculation systems have significantly different operating requirements, their estimated costs are presented separately. Flow-Through System Operational & Maintenance Costs Flow-through systems are mechanically simple, which limits the amount of specialized 7.2.1. maintenance and reduces the potential for extensive equipment repairs. Because water is used only once before being discharged to sewer, operating costs are driven primarily by water consumption, while electricity and labour represent smaller portions of the annual budget. A flow-through spray park typically only requires a single-phase, 15-amp, 120-volt electrical connection to operate its control equipment. Actual current draw is expected to remain well below the maximum service capacity. Assuming a continuous operating current of approximately 4 amps during park hours, seasonal electricity consumption is estimated at approximately 400 kWh, with an annual cost of about $200. Water and sewer charges represent the largest operating expense for a flow-through system due to the single-use nature of the water features. Based on an assumed design flow of 12 L/s (190 US gpm), with the push-button activator in use for approximately 25 percent of operating hours, theoretical seasonal water consumption is estimated at 12,960 m³. Actual consumption may be lower based on operating data from comparable local facilities. Using current District utility rates, the combined seasonal water and sewer cost is estimated at more than $16,500. Flow-through systems do not require separate chemical treatment or filtration media costs. Labour requirements for a flow-through spray park are relatively modest. Seasonal startup and winterization are expected to require less than one day of staff time each. During the operating season, approximately one hour per day has been allocated for daily startup procedures, site inspection, cleaning, and basic functionality checks. A further 16 hours per season has been included for minor maintenance, repairs, and spray pad cleaning. Based on these assumptions, approximately 120 hours of staff time would be required each season, representing an estimated labour cost of $6,600. The total estimated annual operating cost is summarized in Table 3.
Table 3: Estimated Seasonal Operating Costs – Flow-Through System
Seasonal Usage
Estimated Seasonal Cost
Expense
Unit Rate
Current BC Hydro rate and base charges Current District utility rates
Electricity
400 kWh
$200
Water and sewer 12,960 m³
$16,500 $6,600 $23,300
Labour
120 hours
$55/hour
Estimated Total
As shown in Table 3, water usage represents the largest component of flow-through operating costs, followed by labour and electricity. These estimates exclude replacement parts and staff or contractor costs associated with major repairs beyond routine seasonal maintenance.
Page 38