District of Hope Spray Park Feasibility Study

Spray Park Feasibility Study

August 5, 2026

District of Hope – Engineering Department

Version 1.0

7. PROJECT COSTS & FUNDING OPPORTUNITIES The development of a spray park represents a significant capital investment that extends beyond initial construction costs. This section summarizes estimated capital and operational costs, along with potential funding opportunities, to support future budgeting and Council decision-making. Capital Costs Preliminary capital costs were developed through discussions with spray park suppliers and municipalities that have recently completed similar projects. Two suppliers (Vortex, represented locally by PlayQuest, and Waterplay, a division of the Makr Group) provided budget pricing and information from recently completed projects to assist in establishing potential construction costs. 7.1. The following estimates are intended for feasibility planning purposes only. Actual project costs will depend on the selected location, spray park size, mechanical system, site servicing requirements, market conditions, and detailed design. Municipal construction cost estimates are commonly classified according to the level of design information available and the anticipated degree of accuracy. As the project advances and decisions are made regarding site selection, project scale, scope, and servicing requirements, estimates can be refined using increasingly detailed design information. Table 1 provides an overview of the standard construction cost estimate classes used for municipal projects.

Table 1: Overview of Classes of Construction Cost Estimates

Estimate Class

Typical Design Completion

Anticipated Accuracy

Basis of Cost Estimate

Conceptual planning and historical cost data with limited project information Preliminary design, conceptual layouts, and major quantities identified Design development, preliminary drawings, and quantity take-offs Detailed design, completed drawings and specifications, and comprehensive quantity take-offs

Class D

0% to 10%

± 30%

Class C

10% to 33%

± 20%

Class B

33% to 85%

± 10%

Class A

85% to 100%

± 5%

Given the conceptual stage of the project, a Class D construction cost estimate has been prepared for preliminary budget planning. A Class D estimate provides an indicative, order-of- magnitude cost based on conceptual project information and carries an anticipated accuracy of approximately ±30 percent. Costs were differentiated by mechanical system type and used to establish approximate unit rates per square foot of wetted spray pad area. The estimates shown in Table 2 are based on moderate-sized facilities, including approximately 2,000 sq. ft. of wetted area for a flow-through system and 1,700 sq. ft. for a recirculation system.