that subdivisions exceeding 30 dwelling units should have more than one point of access; however, many existing subdivisions predate consistent enforcement of this standard or received waivers that were not conditioned on future remediation. The MTP calls for the City to develop a Critical Access Connections program to systematically identify and prioritize these locations. A subdivision or development should be flagged for critical access review if it meets one or more of the following criteria: ■ Serves more than 30 dwelling units from a single point of access ■ The access road exceeds one-half mile in length from the subdivision entrance to the nearest cross-street or arterial ■ The sole access road crosses a floodplain, railroad, or other feature that could be blocked or rendered impassable during an emergency ■ The subdivision falls outside acceptable emergency response travel time thresholds given single-route constraints ■ No secondary emergency access exists, even in the absence of a second public street A GIS-based screening exercise using these criteria would identify the highest-risk locations citywide and enable the City to prioritize remediation investments — whether through new street connections, secondary emergency access easements, or coordination with adjacent landowners and developers. Where new development is proposed adjacent to a single-access subdivision, the City should evaluate opportunities to require or incentivize connectivity improvements as a condition of approval.
Table 8.25: Traffic Impact Analysis vs. Travel Demand Model Traffic Impact Analysis (TIA) Travel Demand Model (TDM) Purpose Evaluate traffic impacts of a Evaluate cumulative travel demand impacts across a sub-regional corridor network
specific development project on the immediately adjacent street network Any rezoning or development with a change in land use; required at TPW discretion for significant transportation concerns Site driveways, adjacent intersections, and nearby street segments Site-generated trip distribution, level of service analysis at key intersections
Up-zoning deviating from Comp Plan or MTP land use model; OR development generating 500+ additional peak hour trips above prior use (TEM Table 12-1) Sub-area or corridor network spanning multiple arterials and jurisdictions Regional travel demand model; may require micro-simulation for complex corridors TPW staff or consultant, potentially in coordination with NCTCOG Potential MTP network amendments; new arterial capacity, interchange, or connectivity investments added to project program May trigger addition, modification, or deletion of arterial network elements in the MTP
Trigger
Geographic scope
Analysis method Who prepares Typical outcome
Applicant, per TEM Chapter 12 requirements; reviewed by TPW
Site access design, turn lane requirements, signal warrants, off-site mitigation conditions Generally no MTP amendment required unless findings reveal a significant gap
MTP implication
8.10.2. Critical Access Connections While the DRI framework addresses the impacts of new development on the network, a parallel concern involves existing development that was built with inadequate access. Fort Worth has a significant number of large single-family residential subdivisions served by a single point of access — a condition that poses serious public health, safety, and welfare risks. A single-access condition creates vulnerability to emergency response delays, evacuation failures, and routine congestion that residents have no alternative route to avoid. These risks are compounded when the sole access road crosses a floodplain, railroad, or other feature susceptible to blockage. Fort Worth’s Traffic Engineering Manual already establishes
293
Prioritized Project List & TIP | Fort Worth Master Transportation Plan