ENVIRONMENTAL CONSIDERATIONS » Floodplain Considerations: Portions of the project fall within FEMA- designated A/E floodplains, which may affect drainage design and require coordination during environmental review and permitting. PROJECT COMPLEXITY The top challenges include ROW constraints, insufficient staging areas, traffic control plan concerns.

PROSPECTIVE PARTNERS

Tarrant County

City of Fort Worth (2026 Bond)

Very Low

PROJECT TIMELINE

2026 2027 2028 2029 2030 2031 2032

Design

ROW, Utility

Construction

City Council Construction Contract Approval

Project Timeline is subject to change