Bonds Ranch Road - Segment 3
BNSF/UP Railroad to Wagley Robertson Road
ENVIRONMENTAL CONSIDERATIONS » Floodplain Considerations: Portions of the project fall within FEMA- designated A/E floodplains, which may affect drainage design and require coordination during environmental review and permitting. PROJECT COMPLEXITY The top challenges include ROW constraints, insufficient staging areas, traffic control plan concerns.
PROSPECTIVE PARTNERS
Tarrant County
City of Fort Worth (2026 Bond)
Very Low
PROJECT TIMELINE
2026 2027 2028 2029 2030 2031 2032
Design
ROW, Utility
Construction
City Council Construction Contract Approval
Project Timeline is subject to change