ProceduresforLandUsePermitApplications,PublicNotice,HearingsandAppeals | Administration
M. Permit issuance
of the need for additional information (“request for revision”) until either the City advises the applicant that the additional information satisfies the City’s request or 14 days after the date the information has been provided, whichever is the earlier date. If the City determines that the correction, study, or other information submitted by the applicant is insufficient, it shall notify the applicant of the deficiencies, and the procedures of this section shall apply as if a new request for revision had been made. i. The department shall set a reasonable deadline for submittal by the applicant of corrections, studies, or other information in response to a request for revision, and shall provide written notification of the deadline to the applicant. The deadline may not exceed 90 days from the date of the request for revision; provided, that an extension of such deadline may be granted upon written request by the applicant providing satisfactory justification for an extension or upon the applicant’s agreement to and compliance with an approved schedule with specific target dates for submitting the full revisions, corrections or other information requested. ii. Applications may be canceled for inactivity if an applicant fails to provide, by such deadline, an adequate response substantively addressing code requirements identified in the written request for revision. iii. When granting a request for a deadline extension, the department shall give consideration to the number of days between receipt by the department
1. Final decisions by the City on all permits and approvals subject to the procedures of this chapter should be issued within 120 days from the date the applicant is notified by the department pursuant to this chapter that the application is complete; provided, that the following shorter time periods should apply for the type of land use permit indicated:
PERMIT ISSUANCE
Permit Type
Issuance Period
New residential building permits
90 days 40 days 15 days
Residential remodels
Residential appurtenances, such as decks and garages
40 days
Residential appurtenances that require substantial site review SEPA exempt clearing and grading
45 days 90 days 40 days
SEPA clearing and grading
Health department review (for projects pending a final department review and/or permit)
The following periods shall be excluded from this 120-day period: a. Any period of time during which the applicant has been requested by the department, hearing examiner or council to correct plans, perform required studies or provide additional information, including road variances and variances required under Chapter 9.04 KCC as adopted by SDC 21.03.050. The period shall be calculated from the date of notice to the applicant
Effective | January 1, 2022
Title 21: Sammamish Development Code | 629