Preliminary Design/PDB Phase I & Phase II/Construction Summary of Funding Sources and Reimbursements as of 09/15/26 ($ in millions) FSK Bridge Project

Prel Design/ PDB Phase I/PDB Phase II Construction Insurance Proceeds in Lieu ER (Quick Release) Funds Congress Approval ER Funds, Tranche #1*** of Federal Funds (#) Congress Approval ER Funds, Tranche #2***

Available Funding Sources/Federal Funds

Costs Incurred

Invoiced to Date Pending Invoices* Balance for Rebuild

$347.89

$347.89

$284.76

$63.13

$0.00

$24.80

$24.80

$23.27

$1.53

$0.00

$217.03

$192.41

$129.69

$62.72

$24.62

$300.04

$0.00

$0.00

$0.00

$300.04

Settlement Funds (^)

$2,072.20

$0.00

$0.00

$0.00

$2,072.20

Total

$2,961.96

$565.10

$437.72

$127.38

$2,396.86

* Invoices under review include: Kiewit, $120.73M, CMI, $1.76M, GEC, $7.00M and Payroll Costs, $5.00M.

Preliminary Design/Phase I and Phase II/Construction Costs Incurred increased $38.92M versus the Summary Report dated 08/31/26.

**Retainage of $19.82M cannot be reimbursed until paid.

***Congress approved additional ER funds requested.

The Summary Table shown above has been updated through 09/15/26.

(#)Insurance Proceeds include $22.89M in interest earned on the Base Insurance Proceeds of $350.00M through 08/31/26. Currently, $10.00M of interest has been approved by FHWA. Awaiting approval of an additional $12.89M as an available funding source for Preliminary Design/PDB Phase I & Phase II/Construction. (^)This amount represents MDTA's Net Settlement Proceeds received from a $2.25B settlement between the owner and operator of the M/V Dali and the State of Maryland.