FSK Bridge Project Salvage & Debris Removal, Preliminary Design/PDB Phase I & Phase II/Construction Summary of Funding Sources and Reimbursements as of 09/15/26
($ in millions)
Available Funding Sources/Federal Funds
All Phases
Costs Incurred
Invoiced to Date Pending Invoices* Balance for Rebuild
Insurance Proceeds in Lieu of Federal Funds Recycling Revenues in Lieu of Federal Funds Recycling Revenues (Non- Federal) MDTA Funds ER (Quick Release) Funds Congress Approval ER Funds, Tranche #1*** Congress Approval ER Funds, Tranche #2***
$372.89
$372.89
$309.76
$63.13
$0.00
$2.90
$2.90
$2.90
$0.00
$0.00
$1.30
$1.30
$1.30
$0.00
$0.00
$13.50
$13.21
$12.10
$1.11
$0.29
$60.00
$60.00
$54.73
$5.27
$0.00
$217.03
$192.41
$129.69
$62.72
$24.62
$300.04
$0.00
$0.00
$0.00
$300.04
Settlement Funds (^)
$2,072.20
$0.00
$0.00
$0.00
$2,072.20
$2,397.15
Total
$3,039.86
$642.71
$510.48
$132.23
This table summarizes all values for Salvage & Debris Removal and Preliminary Design/PDB Phase I & Phase II/Construction. Total Costs Incurred experienced an increase of $38.92M versus the Summary Report dated 08/31/26.
The Summary Table shown above has been updated through 09/15/26.