AUTHORITY PROJECT SUMMARY MA-3024 SYSTEM-WIDE CCTV REPLACEMENT

PIN NUMBER CONTRACT NUMBER CONTRACT TITLE

MDTAPRJ002585 MA-3024-0000 SYSTEM-WIDE CCTV REPLACEMENT

The work to be performed under this contract is located along multiple MDTA facilities including the Baltimore Harbor Tunnel, Fort McHenry Tunnel, Francis Scott Key Bridge, John F. Kennedy Memorial Highway, Thomas J. Hatem Memorial Bridge, Intercounty Connector, and William Preston Lane Jr. Memorial Bridge facilities. The project will upgrade existing CCTV roadway cameras and camera lowering system, upgrade existing tunnel cameras with new PTZ cameras, upgrade existing CCTV security cameras, and upgrade fiber optic communication equipment including a new fiber optic backbone installation.

PROJECT SUMMARY

SCHEDULE

ADVERTISEMENT DATE

($)

6/12/2025

ANTICIPATED NOTICE TO PROCEED DATE

Advertised GOAL (%)

Proposed GOAL (%)

Feb-26

DURATION (CALENDER DAYS)

MBE PARTICIPATION

1,460

OVERALL MBE

18.00% 0.00% 0.00% 0.00% 0.00% 1.00%

18.07% 0.00% 0.00% 0.00% 0.00% 1.00%

AFRICAN AMERICAN ASIAN AMERICAN HISPANIC AMERICAN

WOMEN

VSBE

ENGINEER'S ESTIMATE (EE)

$9,047,780.00

BID RESULTS

BID AMOUNT ($)

% VARIANCE TO EE

NO ☒

BID PROTEST

YES

Aldridge Electric, Inc

9,978,509.27

10%

FUNDING SOURCE

100% TOLL REVENUE